Timeline & Budget

Project Timeline:

  • Demolition of Mission building early 2023
  • New building Construction in spring 2023
  • Completion spring 2024
  • Move in June 2024
  • Base Camp lease ends July 2024

Vacant Men’s Dorm & Common Room at Mission Building (910 W. Holly St)

Project Budget: 23.5 Million

* With continuously changing costs of goods and services the budget is subject to increase or decrease over the course of the project